18.2.237 GENERAL REQUIREMENTS OF THE ENVIRONMENTAL REVIEW PROCESS
Section
75-1-201 requires state agencies to integrate use of the natural
and social sciences and the environmental design arts in planning and in
decision-making, and to prepare a detailed statement (an EIS) on each
proposal for projects, programs, legislation, and other major actions of state
government significantly affecting the quality of the human environment. In
order to determine the level of environmental review for each proposed action
that is necessary to comply with 75-1-201, MCA, the agency shall
apply the following criteria:
(1) The agency shall prepare an EIS as
follows:
(a) whenever an EA indicates that an EIS is necessary; or
(b) whenever, based on the criteria in ARM 18.2.238, the proposed action is a major
action of state government significantly affecting the quality of the human
environment.
(2) An EA may serve any of the following
purposes:
(a) to
ensure that the agency uses the natural and social sciences and the
environmental design arts in planning and decision-making. An EA may be
used independently or in conjunction with other agency planning and decision-making
procedures;
(b) to
assist in the evaluation of reasonable alternatives and the development of
conditions, stipulations or modifications to be made a part of a proposed
action;
(c) to
determine the need to prepare an EIS through an initial evaluation and
determination of the significance of impacts associated with a proposed action;
(d) to
ensure the fullest appropriate opportunity for public review and comment on
proposed actions, including alternatives and planned mitigation, where the
residual impacts do not warrant the preparation of an EIS; and
(e) to
examine and document the effects of a proposed action on the quality of the
human environment, and to provide the basis for public review and comment,
whenever statutory requirements do not allow sufficient time for an agency to
prepare an EIS. The agency shall determine whether sufficient time is available
to prepare an EIS by comparing statutory requirements that establish when the
agency must make its decision on the proposed action with the time required by
ARM 18.2.246 to obtain public review of an EIS plus a reasonable period to
prepare a draft EIS and, if required, a final EIS.
(3) The agency shall prepare an EA whenever:
(a) the action is not excluded under (5) and it is not clear without preparation of an EA whether the proposed action is
a major one significantly affecting the quality of the human environment;
(b) the
action is not excluded under (5) and although an EIS is not warranted, the
agency has not otherwise implemented the interdisciplinary analysis and public
review purposes listed in (2) (a) and (d) through a similar planning and
decision-making process; or
(c) statutory requirements do not allow sufficient time for the agency to prepare
an EIS.
(4) The
agency may, as an alternative to preparing an EIS, prepare an EA whenever the
action is one that might normally require an EIS, but effects which might
otherwise be deemed significant appear to be mitigable below the level of
significance through design, or enforceable controls or stipulations or both
imposed by the agency or other government agencies. For an EA to suffice in this
instance, the agency must determine that all of the impacts of the proposed
action have been accurately identified, that they will be mitigated below the
level of significance, and that no significant impact is likely to occur. The
agency may not consider compensation for purposes of determining that impacts
have been mitigated below the level of significance.
(5) The
agency is not required to prepare an EA or an EIS for the following categories
of action:
(a) actions that qualify for a categorical exclusion as defined by rule or
justified by a programmatic review. In the rule or programmatic review, the
agency shall identify any extraordinary circumstances in which a normally
excluded action requires an EA or EIS;
(b) administrative actions: routine, clerical or similar functions of a department,
including but not limited to administrative procurement, contracts for
consulting services, and personnel actions;
(c) minor repairs, operations, or maintenance of existing equipment or facilities;
(d) investigation and enforcement: data collection, inspection of facilities or
enforcement of environmental standards;
(e) ministerial actions: actions in which the agency exercises no discretion, but
rather acts upon a given state of facts in a prescribed manner; and
(f) actions that are primarily social or economic in nature and that do not
otherwise affect the human environment.
History: Sec. 2-3-103, 2-4-201, MCA; IMP, Sec. 2-3-104, 75-1-201, MCA; NEW, 1988 MAR p. 2692, Eff. 12/23/88.