38.5.8406 REVIEW PROCEDURES (1) An EDC shall review interconnection requests using one or more of the following review procedures: (a) An EDC shall use Level 1 procedures for evaluation of all interconnection requests to connect inverter-based small generation facilities if: (i) The small generator facility has a nameplate capacity of 50 kW or less; and (ii) The customer interconnection equipment proposed for the small generator facility is certified. (b) An EDC shall use Level 2 procedures for evaluating interconnection requests if: (i) The small generator facility has a nameplate capacity of 2 MW or less; and (ii) The interconnection equipment proposed for the small generator facility is certified; or (iii) The small generator facility was reviewed under Level 1 review procedures but not approved and the applicant has submitted a new interconnection request for consideration. (c) An EDC shall use Level 3 review procedures for evaluating interconnection requests where power will not be exported. (d) An EDC shall use the Level 4 study procedures for evaluating interconnection requests if: (i) The interconnection request was not approved under a Level 1, Level 2, or Level 3 expedited review and the applicant has submitted an interconnection request for consideration under a Level 4 study review; or (ii) The interconnection request does not meet the criteria for expedited review under Level 1, Level 2, or Level 3 review procedures. History: 69-3-103, MCA; IMP, 69-3-102, MCA; NEW, 2010 MAR p. 1801, Eff. 8/13/10. |