Rule Title: FORFEITURE OF BOND
Add to My Favorites
Add to Favorites
Department: ENVIRONMENTAL QUALITY
Chapter: ENERGY
Subchapter: Solar and Wind Generation Facility Decommissioning and Bonding
 
Latest version of the adopted rule presented in Administrative Rules of Montana (ARM):

Printer Friendly Version

17.86.121    FORFEITURE OF BOND

(1) If an owner fails to decommission a facility in either the manner or schedule set forth in the decommissioning plan under ARM 17.86.105 and did not commence action to rectify deficiencies within 90 days after the department's notification was mailed, the department may cause the bond to be forfeited for the entire facility. The department shall notify the owner and the surety by certified mail.

(2) The notification in (1):

(a) must include the reasons for forfeiture and the amount to be forfeited; and

(b) is a final decision of the department.

 

History: 75-26-310, MCA; IMP, 75-26-309, MCA; NEW, 2018 MAR p. 94, Eff. 1/13/18; AMD, 2020 MAR p. 957, Eff. 5/30/20.


 

 
MAR Notices Effective From Effective To History Notes
17-409 5/30/2020 Current History: 75-26-310, MCA; IMP, 75-26-309, MCA; NEW, 2018 MAR p. 94, Eff. 1/13/18; AMD, 2020 MAR p. 957, Eff. 5/30/20.
17-394 1/13/2018 5/30/2020 History: 75-26-310, MCA; IMP, 75-26-309, MCA; NEW, 2018 MAR p. 94, Eff. 1/13/18.
Home  |   Search  |   About Us  |   Contact Us  |   Help  |   Disclaimer  |   Privacy & Security