HOME    SEARCH    ABOUT US    CONTACT US    HELP   
           
Rule: 38.5.1908 Prev     Up     Next    
Rule Title: INFORMATION TO BE PROVIDED TO THE COMMISSION
Add to My Favorites
Add to Favorites
Department: PUBLIC SERVICE REGULATION
Chapter: UTILITY DIVISION
Subchapter: Cogeneration and Small Power Production
 
Latest version of the adopted rule presented in Administrative Rules of Montana (ARM):

Printer Friendly Version

38.5.1908    INFORMATION TO BE PROVIDED TO THE COMMISSION

(1) Pursuant to initial contact with a potential qualifying facility, each utility shall provide the Commission with one electronic copy of the utility's initial written response.

(2)  No later than July 1 of each even-numbered year, each utility shall file with the Commission the following cost data:

(a)  the estimated avoided cost of energy as required by 18 CFR 292.302(b)(1);

(b)  the electric utility's latest resource plan, including any supplements, as required by 18 CFR 292.302(b)(2); and

(c)  the estimated capacity costs as required by 18 CFR 292.302(b)(3).  These costs shall represent the avoidable resources in the utility's resource plan.

 

History: 69-3-103, MCA; IMP, 69-3-102, MCA; NEW, 1981 MAR p. 459, Eff. 5/15/81; AMD, 2022 MAR p. 1919, Eff. 9/24/22.


 

 
MAR Notices Effective From Effective To History Notes
38-5-254 9/24/2022 Current History: 69-3-103, MCA; IMP, 69-3-102, MCA; NEW, 1981 MAR p. 459, Eff. 5/15/81; AMD, 2022 MAR p. 1919, Eff. 9/24/22.
5/15/1981 9/24/2022 History: 69-3-103, MCA; IMP, 69-3-102, MCA; NEW, 1981 MAR p. 459, Eff. 5/15/81.
Home  |   Search  |   About Us  |   Contact Us  |   Help  |   Disclaimer  |   Privacy & Security