(1) The engineering report must include detailed
descriptions and design assumptions for the removal, partial removal, or
abandonment of the dam.
(2) Plans and specifications must include as a minimum the following:
(a) a cover sheet indicating the name of the project, name of owner, certification
by the engineer and the owner pursuant to ARM 36.14.304 (2b) , designated access
to the site, and the location with respect to highways, roads, and streams;
(b) method of draining the reservoir during removal and statement of the sequence
of operations;
(c) method of disposal or stabilization of the sediment;
(d) disposition of the dam materials;
(e) description of the reclamation actions to be applied to the dam and impoundment
area; and
(f) means for removal of the dam to prevent future impoundment.