(1) Pursuant to initial contact with a potential qualifying facility, each utility shall provide the Commission with one electronic copy of the utility's initial written response.
(2) No later than July 1 of each even-numbered year, each utility shall file with the Commission the following cost data:
(a) the estimated avoided cost of energy as required by 18 CFR 292.302(b)(1);
(b) the electric utility's latest resource plan, including any supplements, as required by 18 CFR 292.302(b)(2); and
(c) the estimated capacity costs as required by 18 CFR 292.302(b)(3). These costs shall represent the avoidable resources in the utility's resource plan.