17.36.802 FEE SCHEDULES (1) An applicant for approval of a division of land into one or more parcels, condominiums, mobile home/trailer courts, recreational camping vehicle spaces, and tourist campgrounds shall pay the following fees:
|
UNIT |
UNIT COST |
TYPE OF LOTS |
|
|
Subdivision lot |
lot/parcel |
$ 100 |
Condominium/trailer court/recreational camping vehicle campground |
unit/space |
$ 40 |
Resubmittal fee – previously approved lot, boundaries are not changed |
lot/parcel |
$ 60 |
TYPE OF WATER SYSTEM |
|
|
Individual or shared water supply system (existing and proposed) |
unit |
$ 60 |
Multiple user system - new system
- connection to approved existing distribution system - extension to existing distribution system - new distribution system |
each
lot/unit
lot/unit
lot/unit |
$250 (plus $75/ hour for review in excess of four hours)
$ 20
$ 50
$ 50 |
Public water system New system per DEQ-1
- connection to existing system - extension of existing system - new distribution system |
component
lot/structure lot/structure lot/structure
|
per ARM 17.38.106 fee schedule
$ 20 $ 40 $ 40 |
TYPE OF WASTEWATER DISPOSAL |
|
|
Existing systems |
unit |
$ 60 |
New subsurface system |
drainfield |
$ 75 |
New pressure-dosed, elevated sand mound, ET systems, intermittent sand filter, ETA systems, recirculating sand filter, recirculating trickling filter, aerobic treatment unit, nutrient removal, and whole house subsurface drip irrigation systems |
design |
$150 (plus $75/ hour for review in excess of two hours) |
Drainfields for pressured-dosed, intermittent sand filter, recirculating sand filter, recirculating trickling filter, aerobic treatment unit, and nutrient removal |
drainfield |
$ 40 |
|
UNIT |
UNIT COST |
Gray water reuse systems. This is a stand- alone fee and all gray water reuse systems will be reviewed at the unit cost |
unit |
$75 (plus $75/hour in excess of two hours) |
Multiple user wastewater system - connection - extension - new collection system |
lot/unit lot/unit lot/unit |
$ 20 $ 50 $ 50 |
New public wastewater system per DEQ-2
- New connection to existing system - New extension to existing public wastewater system - New public wastewater collection system
|
component
lot/structure
lot/structure
lot/structure |
per ARM 17.38.106 fee schedule
$ 20
$ 50
$ 50 |
OTHER |
|
|
Deviation from circular |
request or per design |
$150 (plus $75/ hour for review in excess of two hours) |
Waiver from rule |
request |
$150 (plus $75/ hour for review in excess of two hours) |
Reissuance of original approval statement |
request |
$ 50 |
Municipal facilities exemption checklist (former master plan exemption) |
application |
$ 100 |
|
UNIT |
UNIT COST |
Nonsignificance determinations/categorical exemption reviews - individual/shared systems
- multiple-user and public systems |
drainfield
lot/structure |
$ 50
$ 25 |
Storm drainage plan review
- plans exempt from Circular DEQ-8
- Circular DEQ-8 review |
lot
lot |
$ 30
$30 (plus $75/ hour for review in excess of 30 minutes per lot) |
Preparation of environmental assessments/environmental impact statements |
---- |
actual cost | History: 76-4-105, MCA; IMP, 76-4-105, 76-4-128, MCA; NEW, EMERG, Eff. 5/15/75; NEW, Eff. 9/5/75; AMD, Eff. 5/6/76; AMD, EMERG, 1977 MAR p. 536, Eff. 9/6/77; AMD, 1977 MAR p. 750, Eff. 10/25/77; AMD, 1980 MAR p. 2967, Eff. 11/29/80; AMD, 1981 MAR p. 1288, Eff. 10/30/81; AMD, 1983 MAR p. 851, Eff. 7/15/83; AMD, 1984 MAR p. 1027, Eff. 7/13/84; AMD, 1992 MAR p. 2145, Eff. 9/25/92; AMD, 1993 MAR p. 542, Eff. 4/16/93; TRANS, from DHES, 1996 MAR p. 1499; AMD, 1998 MAR p. 646, Eff. 3/13/98; AMD, 2002 MAR p. 1465, Eff. 5/17/02; AMD, 2009 MAR p. 2477, Eff. 12/25/09.
|