(1) Plan review fees must be paid before the department will issue a license.
(2) If the department requires plan review at identified phases of construction of water parks or complex projects to ensure that the construction is in compliance with the plans, any interim fee outlined in Table 1 must be paid at the time of each such additional review. The fee applies to each pool, spa, or other water feature.
(3) The plan review fee for any pre-opening of a pool, spa, or other water feature is outlined in Table 1. A pre-opening fee applies to each pool, spa, or other water feature opening at the facility to ensure that construction is in compliance with the plan.