24.301.536 APPLICATION FOR IN-PLANT QUALITY CONTROL MANUAL REVIEW
(1) Manufacturers of units shall make application to the bureau for an in-plant quality control manual review. The application submittal shall contain at least the following:
(a) an outline of the procedure which will direct the manufacturer to construct units in accordance with the reviewed plans as set forth in ARM 24.301.543;
(b) one copy of all documents submitted for review, which shall be on substantial paper or cloth not less than 8 1/2" x 11" or electronically in a format acceptable to the department;
(c) an application on forms supplied by the bureau; and
(d) inspection fees as required by ARM 24.301.565.
History: 50-60-203, 50-60-401, MCA; IMP, 50-60-203, 50-60-401, 50-60-402, MCA; NEW, Eff. 3/1/75; AMD, Eff. 4/4/77; TRANS, from Dept. of Admin., Ch. 352, L. 1985, Eff. 7/1/85; AMD, 1994 MAR p. 299, Eff. 2/11/94; TRANS, from Commerce, 2001 MAR p. 2301; AMD, 2016 MAR p. 887, Eff. 5/21/16.