38.5.812 REQUIREMENTS FOR THE SUBMISSION OF OMITTED INFORMATION
(1) For utility applications made pursuant to 69-3-308, MCA if a utility has not complied with the minimum filing standards of this subchapter or has otherwise failed to provide information as provided for in the proceeding to consider the filing, the commission may order within forty-five days of receipt of the utility's application that the utility address these omissions and continue the proceeding until they are addressed.
(2) For utility applications made pursuant to 69-3-302, MCA, a filing made by a utility which does not include the information required by this subchapter, the remedies provided for in ARM 38.5.184 apply.
(3) This rule does not affect the commission's ability to pursue the remedies provided for in 69-3-206 and 69-3-208, MCA.
History: 69-3-103, 69-3-310, MCA; IMP, 69-3-202, 69-3-206, 69-3-208, 69-3-302, 69-3-308, MCA; NEW, 2017 MAR p. 790, Eff. 6/10/17.