(1) An application must include:
(a) either a copy of any and all interconnection and transmission agreements involving the proposed facility, or the following information for each such agreement:
(i) a brief description of the obligations of and the benefits to the facility under the agreement;
(ii) a list of all parties to the agreement;
(iii) the time period during which the agreement is in effect;
(iv) a summary of the terms of the agreement; and
(v) the financial agreements; and
(b) a description of all current and planned negotiations with respect to interconnection of the facility and transmission of energy. � The description must include a list of the parties to any negotiations and a general discussion of the history and current status of the negotiations.
�