17.20.1507    ENERGY GENERATION AND CONVERSION FACILITIES, INTERCONNECTION AND TRANSMISSION AGREEMENTS

(1) An application must include:

(a) either a copy of any and all interconnection and transmission agreements involving the proposed facility, or the following information for each such agreement:

(i) a brief description of the obligations of and the benefits to the facility under the agreement;

(ii) a list of all parties to the agreement;

(iii) the time period during which the agreement is in effect;

(iv) a summary of the terms of the agreement; and

(v) the financial agreements; and

(b) a description of all current and planned negotiations with respect to interconnection of the facility and transmission of energy. � The description must include a list of the parties to any negotiations and a general discussion of the history and current status of the negotiations.

History: 75-20-105, MCA; IMP, 75-20-211, MCA; NEW, 2001 MAR p. 2410, Eff. 12/7/01.